SUPERINTENDENT'S DAILY REPORT |
|
|
|
|
|
|
|
| DATE: |
9/23/2003 |
|
|
|
|
|
|
|
|
|
|
| PROJECT: |
|
|
|
|
|
|
|
|
|
|
|
| WEATHER: |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| SCHEDULE |
ORIGINAL FINISH |
CURRENT |
CAL. DAYS |
|
|
|
|
|
|
|
| STATUS |
06/23/04 |
6/22/04 |
1.21 |
Days Ahead Schedule |
| |
|
|
|
|
|
|
|
|
|
|
|
| INSPECTIONS |
LOCATION |
TYPE |
PASS |
FAIL |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| VISITORS |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| COMMENTS |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| SUBCONTRACTORS CONTACTED |
|
|
|
|
|
|
|
|
|
|
| Subcontractor |
Task |
Person |
Date Scheduled |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| PROJECT SUPERINTENDENT |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Daily Schedule |
|
|
|
|
PM |
AM |
PM |
| SUBCONTRACTOR |
TASK |
SCHED START |
FINISH |
% |
CRITICAL |
commitment from foreman for tomorrow's priorities |
contacted to communicate tomorrow's priorities |
# Employees working on tasks |
commitment from foreman |
contacted to communicate today's priorities |
Update Remaining Duration for all tasks |
| ABATEMENT AND DEMOLITION |
ABATEMENT AND DEMOLITION |
06/02/03 |
07/28/03 |
0% |
x |
|
|
|
|
|
41 days |
| CONCRETE |
EXCAVATE AND POUR FOOTINGS |
09/23/03 |
10/06/03 |
0% |
x |
|
|
|
|
|
10 days |
| ELECTRICAL |
ELECTRICAL ROUGH UNDER SLAB |
09/02/03 |
09/22/03 |
0% |
x |
|
|
|
|
|
15 days |
| EXCAVATION |
EXCAVATE BUILDING PAD |
07/29/03 |
08/11/03 |
0% |
x |
|
|
|
|
|
9.5 days |
| EXCAVATION |
FILL BUILDING PAD |
08/12/03 |
09/01/03 |
0% |
x |
|
|
|
|
|
15 days |
| PLUMBING |
PLUMBING UNDER SLAB |
09/02/03 |
09/22/03 |
0% |
x |
|
|
|
|
|
15 days |
| QUALITY CONTROL |
UNDERGROUND UTILITIES INSPECTION |
08/26/03 |
08/26/03 |
0% |
|
|
|
|
|
|
1 day |
| QUALITY CONTROL |
SITE SANITARY INSPECTION |
08/26/03 |
08/26/03 |
0% |
|
|
|
|
|
|
1 day |
| QUALITY CONTROL |
SITE ELECTRICAL INSPECTION |
08/26/03 |
08/26/03 |
0% |
|
|
|
|
|
|
1 day |
| QUALITY CONTROL |
PLUMBING SLAB INSPECTION |
09/16/03 |
09/22/03 |
0% |
|
|
|
|
|
|
5 days |
| BASEBALL FIELD |
BASEBALL FIELD |
06/02/03 |
09/29/03 |
0% |
|
|
|
|
|
|
86 days |
| ELECTRICAL |
UNDERGROUND TELEPHONE CONDUIT |
08/26/03 |
09/08/03 |
0% |
|
|
|
|
|
|
10 days |
| ELECTRICAL |
UNDERGROUND FIBER OPTIC CONDUIT |
08/26/03 |
09/08/03 |
0% |
|
|
|
|
|
|
10 days |
| ELECTRICAL |
ELECTRICAL CONDUIT AT SITE LIGHTING |
08/26/03 |
09/01/03 |
0% |
|
|
|
|
|
|
5 days |
| ELECTRICAL |
ELECTRICAL WIRE AT SITE LIGHTING |
09/02/03 |
09/08/03 |
0% |
|
|
|
|
|
|
5 days |
| ELECTRICAL |
HAUL ELECTRICAL SPOILS |
09/23/03 |
09/29/03 |
0% |
|
|
|
|
|
|
5 days |
| ELECTRICAL |
UNDERGROUND PRIMARY SERVICE CONDUIT TO TRANSFORMER |
09/23/03 |
09/29/03 |
0% |
|
|
|
|
|
|
5 days |
| ELECTRICAL |
INSTALL GROUND ROD |
09/23/03 |
09/23/03 |
0% |
|
|
|
|
|
|
1 day |
| EXCAVATION |
EXCAVATE SITE |
08/12/03 |
08/25/03 |
0% |
|
|
|
|
|
|
10 days |
| EXCAVATION |
HAUL EXCAVATED SPOILS |
08/26/03 |
09/01/03 |
0% |
|
|
|
|
|
|
5 days |
| PREENGINEERED METAL BUILDING |
CONTRACT PREENGINEERED BUILDING FOR CANNING |
06/13/03 |
06/19/03 |
0% |
|
|
|
|
|
|
5 days |
| PREENGINEERED METAL BUILDING |
SUBMITTALS PREENGINEERED BUILDING FOR CANNING |
09/08/03 |
10/31/03 |
0% |
|
|
|
|
|
|
40 days |
| SITE UTILITIES |
SITE SANITARY SEWER |
08/26/03 |
09/01/03 |
0% |
|
|
|
|
|
|
5 days |
| SITE UTILITIES |
SITE STORM SEWER |
08/26/03 |
09/08/03 |
0% |
|
|
|
|
|
|
10 days |
| SITE UTILITIES |
SITE WATER SERVICE |
09/02/03 |
09/08/03 |
0% |
|
|
|
|
|
|
5 days |
| SITE UTILITIES |
STORM SEWER UNDER SLAB |
09/02/03 |
09/08/03 |
0% |
|
|
|
|
|
|
5 days |
| SITE UTILITIES |
SITE FIRE LINE |
09/02/03 |
09/08/03 |
0% |
|
|
|
|
|
|
5 days |